Acts and Regulations

2013, c.7 - Electricity Act

Full text
Review of approved transmission tariff
116(1)On request of the Lieutenant-Governor in Council or on its own motion, the Board may review all or any portion of the approved transmission tariff.
116(2)On a review under subsection (1), the Board shall
(a) direct the Corporation to file an application for confirmation of any portion or all of the approved transmission tariff,
(b) give notice to the transmitters of the date of the hearing of the application, and
(c) proceed under section 127.
116(3)If, in the course of a review under this section, the Board is of the opinion that there is likely to be a material change to a transmitter’s transmission revenue requirements, the Board may require the transmitter to attend the hearing for the purpose of defending those transmission revenue requirements, in which case the transmitter shall be deemed to be a party to the proceedings before the Board.
116(4)The Board, at the conclusion of the hearing, shall
(a) confirm the transmission tariff, if it is satisfied that the transmission tariff is just and reasonable, or if not so satisfied, fix any other transmission tariff that it finds to be just and reasonable, and
(b) set the time at which any change in the transmission tariff is to take effect.
Review of approved transmission tariff
116(1)On request of the Lieutenant-Governor in Council or on its own motion, the Board may review all or any portion of the approved transmission tariff.
116(2)On a review under subsection (1), the Board shall
(a) direct the Corporation to file an application for confirmation of any portion or all of the approved transmission tariff,
(b) give notice to the transmitters of the date of the hearing of the application, and
(c) proceed under section 127.
116(3)If, in the course of a review under this section, the Board is of the opinion that there is likely to be a material change to a transmitter’s transmission revenue requirements, the Board may require the transmitter to attend the hearing for the purpose of defending those transmission revenue requirements, in which case the transmitter shall be deemed to be a party to the proceedings before the Board.
116(4)The Board, at the conclusion of the hearing, shall
(a) confirm the transmission tariff, if it is satisfied that the transmission tariff is just and reasonable, or if not so satisfied, fix any other transmission tariff that it finds to be just and reasonable, and
(b) set the time at which any change in the transmission tariff is to take effect.